spot_img
28.7 C
Philippines
Saturday, April 27, 2024

NGCP asks ERC to approve 6 projects worth P20 billion

- Advertisement -
- Advertisement -

Transmission operator National Grid Corp. of the Philippines asked the Energy Regulatory Commission to approve six transmission projects with a combined cost of P20 billion.

NGCP refiled the projects for approval after withdrawing the previous application, citing several factors that contributed to the increase in project costs and/or change in components of the six projects.

“To avoid disruption of operation and to ensure continuous compliance with NGCP’s mandate under the EPIRA [Electric Power Industry Reform Act] as the transmission operator, it is imperative that the implementation of the proposed capex projects be immediately approved,” NGCP said.

The refiled projects include the P1-billion Concepcion-Sta. Ignacia 69kV Transmission Line Project, which aims to address the overloading of the Concepcion-Camiling 69 kV Transmission Line and provide additional transmission capacity to cater to the growing power demand in the Tarlac area.

The project will unload the existing Concepcion-Camiling 69 kV Transmission Line and cater to the loads of Tarlac Electric Cooperative I in Sta. Ignacia, Camiling, Mayantoc, Paniqui, Moncada and Anao.

- Advertisement -

It will be implemented for 66 months.

NGCP also sought approval for the P4.415-billion  San Simon 230kV Substation Project which will accommodate the growing demand of existing steel mills and directly connected industries and support the entry of new steel mills and industrial loads in San Simon, Pampanga.

It will also address the overloading of various 69 kV transmission facilities and serve as an alternate source substation for the loads connected at Mexico Substation.

The project will be implemented over 68 months.

NGCP also refiled the Pinili 230kV Substation Project for approval to address the forecasted load growth in Ilocos Region. The project will serve as the new connection point for future renewable energy power plants in the area.

The total estimated project cost is P1.64 billion to be implemented over 62 months.

NGCP is also seeking ERC approval for the Laray 230kV Substation Project to prevent the overloading of the Quiot and Cebu substations.

The project will also ensure the reliability of power delivery in Metro Cebu through load shifting between substations during N-1 contingency.

The P6.35-billion project will accommodate future developments and provide new terminations for customers in the area. It will be implemented over 147 months.

NGCP is seeking approval for the Calbayog-Allen Transmission Line Project to improve the reliability of power delivery in Northern Samar.

The proposed San Isidro 138 kV Substation will be constructed to accommodate the load growth in Northern Samar and the entry of the San Isidro Wind Farm of Lihangin Wind Energy Corporation in Northern Samar.

The estimated project cost is P3.31 billion, with an implementation period of 103 months.

NGCP asked ERC to approve the P3.6 billion Maco-Mati 138kV Transmission Line Project to provide a  grid connection point for  Davao Oriental  Electric Cooperative.

The project will relieve the imminent overloading of the existing Maco-Banaybanay 69 kV Line serving Doreco and Northern Davao Electric Cooperative.

It will boost the economy of Mati City through nearby transmission and substation facilities with bigger loading capacities. It will be implemented over 36 months.

- Advertisement -

LATEST NEWS

Popular Articles