Meralco recently commissioned the new Vermosa South 115 kV – 34.5 kV Substation located near Daang Hari Road in Imus, Cavite.
![](https://cdn.manilastandard.net/wp-content/uploads/2023/08/20230507_021107-1024x577.jpg)
This aims to relieve the neighboring Imus power transformer bank 2 and cater to the growing demand in the area as well as large-load customers such as SM City Molino, The District Dasmariñas, Ayala Vermosa Sports Hub, and Westfield Subdivision.
![](https://cdn.manilastandard.net/wp-content/uploads/2023/08/DJI_0126-1024x576.jpg)
The project includes the construction of a new 5-km 115-kV sub-transmission line running along Daang-Hari Road which cuts into the existing Dasmariñas-Abubot-SMC-Imus Line. Meralco is continuously working to improve its distribution system to deliver safe, adequate, reliable, and sustainable power service to its customers as part of its commitment to #KeepingTheLightsOn and #PoweringTheGoodLife.