Light Rail Manila Corp., operator of Light Rail Transit Line 1, said the construction progress of the LRT-1 Cavite Extension reached a completion rate of 36.8 percent since the start of civil works in September 2019. 

LRMC said the pre-cast yard and staging area were completed, with pillars already built along the stretch of Dr. Santos Station until MIA Station.

- Advertisement -

It said that with the construction works in full swing, a temporary road closure of the inner most lane (northbound) along Cavitex-Paranaque bridge was set for implementation from March 17 to 31, 2020. 

This is to give way to the scheduled test pit works (bridge and pipe inspection) required for the construction in the area relative to the LRT-1 Cavite Extension project.

 “We would like to request for the understanding and cooperation of all motorists using the Cavitex. The temporary road closure of one lane is necessary to prepare the foundations needed to construct the LRT-1 Cavite Extension in the area and complete it as scheduled,” said LRMC Cavite Extension Management Team project execution manager Reynaldo Pangilinan.