Almost finished

- Advertisement -

This aerial photo shows two bridge segments of the Cebu-Cordova Link Expressway (CCLEX), now only 152 meters apart, with 34 out of 56 cables already installed to complete the entire tollway bridge, as riders are treated to the scenic Mactan Channel. Construction activity has been nonstop to beat the deadline of substantial completion by yearend 2021 and set for full commercial operations within the first quarter of 2022.