NLEX Marilao finishes repair, opens all lanes

Estimated reading time: 1 minute and 24 seconds
16px

NLEX Corp. said Wednesday all four lanes of North Luzon Expressway’s Marilao northbound section are now passable to vehicles ahead of the projected schedule.

“While all lanes are now passable, supporting steel poles will remain on the lanes to allow concrete curing of the bridge. With this development, traffic flow in Marilao Northbound is expected to improve and normalize in the next few days,” NLEX said in a statement.

- Advertisement -

The Marilao Bridge sustained damage from a truck violating regulations on March 19, causing traffic flow changes to facilitate ongoing repairs and ensure motorists’ safety.

Originally scheduled for completion in two weeks, NLEX expedited the repairs, with teams working around the clock and with the expedited delivery of the fabricated steel needed for the bridge.

“We thank the motoring public for their utmost understanding and patience while repairs were ongoing,” NLEX said.

“Rest assured that NLEX continues to intensify safety and traffic measures in key areas of the expressway to ensure the safety and convenience of our valued customers,” it said.

The Department of Transportation (DOTr), in a separate statement, thanked NLEX for the swift response to open all four lanes under the damaged Marilao Interchange Bridge on NLEX. This was done a week ahead of the original two-week schedule.

“This will now allow close to normal travel times, so that commuters and motorists on NLEX can spend more valuable time with their families and reach their destinations promptly,” the DOTr said.

“This shows the commitment and dedication of both the DOTr and its partners like NLEX Corp. to respond quickly to problems such as this to try and provide a seamless and comfortable travel experience for all Filipinos,” it said.