NGCP’s PhP67.98 Billion Cebu-Negros-Panay 230kV Backbone energized

Showcasing the strengthening and continued improvement of the transmission network in the Visayas, NGCP held a simultaneous ceremonial energization and inauguration of its newly completed Cebu-Negros-Panay (CNP) 230-kiloVolt (kV) Backbone on Monday, 08 April 2024, in the provinces of Iloilo, Negros Occidental, and Cebu.

- Advertisement -

His Excellency Ferdinand R. Marcos Jr, along with NGCP President and CEO Anthony L. Almeda, Vice Chairman Henry Sy Jr., Chief Technical Officer Rico Vega, and DOE Secretary Raphael Lotilla inspected Bacolod Substation switchyard prior to the official inauguration ceremony of CNP Project.

The event was held simultaneously at NGCP’s Bacolod Substation in Negros Occidental, led by His Excellency President Ferdinand R. Marcos, Jr., NGCP’s Barotac Viejo Substation in Iloilo, and Magdugo Substation in Cebu, with key national and local government officials also in attendance.

“This monumental milestone represents a significant step towards ensuring a stable transmission grid in the Philippines, and we are honored to lead and witness its completion. NGCP has consistently worked towards meeting its commitment to provide a reliable electricity infrastructure for the nation, and the CNP is a testament to our dedication to enhancing the power transmission capabilities of our country,” the company said.

The Cebu-Negros-Panay Backbone which also include the Negros-Panay Interconnection Project Line 2, is comprised of three stages, the last of which was completed on 27 March 2024. This complements the existing Amlan-Samboan submarine cable which is currently utilized to connect Cebu and Negros islands. The first stage of the CNP Project added a new 230kV transmission line from Bacolod to E.B Magalona, while the 2nd stage upgraded the Cebu Substation into 230kV level.

The CNP is comprised of 670 transmission towers spanning 442 circuit kilometers of overhead lines, 98.9 circuit kilometers of submarine cables with 10 new substations and the expansion of 2 existing major substations.

While certified as an Energy Project of National Significance (EPNS) in 2019, the project still encountered various difficulties particularly on right-of-way issues due to opposition of landowners, long and tedious judicial processes, protracted permitting processes by local government units, unreasonable demands and threats from a particular barangay official, security issues in certain areas in Negros, and the COVID-19 pandemic in 2020. In September2023, the Cebu-Magdugo 230kV line was also the subject of a Temporary Restraining Order (TRO) issued by the Supreme Court.

“Despite the various challenges surrounding the completion of the CNP, NGCP’s commitment to delivering this important project did not falter. The dedication of our personnel who worked despite security threats, inclement weather conditions and difficult terrain, and the support of concerned government agencies that assisted us were instrumental in driving this project forward,” said NGCP.

The project was filed for approval with the Energy Regulatory Commission (ERC) in four stages as early as 2013. The CNP Stage 3 was filed in 2016 with a project cost of PhP43.41 Billion. However, the ERC granted a provisional approval for only one year’s worth of capital expenditure amounting to PhP176.75 Million in 2017 and has yet to issue a final approval. The total cost of the entire CNP backbone project as filed with the ERC, amounts to PhP67.98 Billion. Line 2 of the Negros-Panay Interconnection Project is still pending approval by ERC.

“While the CNP will help improve the delivery of power, this is not the sole or primary solution to the woes of power consumers, particularly in Panay. Sufficient power generation supported by reliable transmission is the formula for optimized energy development. This will support the country’s push towards economic recovery,” said NGCP. 