Ayala, MPIC expect to start LRT project

Light Rail Manila Corp., a consortium led by Ayala Corp. and Metro Pacific Investments Corp., said it will accelerate the construction of Light Rail Transit Line 1 Cavite extension project to meet the 2019 target completion date. 

“We are hoping that we can give the notice to proceed within the year. The target date [of completion] would be 2019.  Hopefully we should be done, but we will see if we can still meet the target,” LRMC president and chief executive Jesus Francisco said. 

The project is expected to be fully operational by May 2019.

Francisco said the company was expecting the government to deliver the remaining right of way this month. 

“We are waiting for the right of way and we are also awaiting the relocation of the informal settlers. By October, hopefully they [the government] would be able to do that,” Francisco said. 

LRMC is a responsible for the construction of the 11.7-kilometer extension from the present end point in Baclaran to the Niog area in Bacoor, Cavite. The project cost is almost over P40 billion, which includes the rehabilitation of  LRT Line 1 and the extension of the system to Cavite. 

Topics: Light Rail Manila Corp. , Ayala Corp. , Metro Pacific Investments Corp. , Light Rail Transit Line 1 Cavite extension
COMMENT DISCLAIMER: Reader comments posted on this Web site are not in any way endorsed by Manila Standard. Comments are views by manilastandard.net readers who exercise their right to free expression and they do not necessarily represent or reflect the position or viewpoint of manilastandard.net. While reserving this publication’s right to delete comments that are deemed offensive, indecent or inconsistent with Manila Standard editorial standards, Manila Standard may not be held liable for any false information posted by readers in this comments section.